Why this trade-off keeps surfacing in bank transformations
In transformation programs, the argument between “stay on the critical path” and “deliver quick wins” is rarely a disagreement about priorities. It is a proxy for a deeper constraint: portfolio capacity. Banks are typically running multiple mandatory commitments at once, including regulatory change, resilience remediation, platform modernization, and customer-facing roadmaps. When change capacity is finite, every quick win consumes people, governance attention, and production change slots that could otherwise protect the structural path to the target state.
The result is a predictable pattern. Programs that focus only on the critical path can become politically fragile as stakeholders see few near-term outcomes. Programs that focus only on quick wins can achieve local improvements while the enterprise backbone remains unchanged, leaving the bank with higher complexity and limited strategic progress. The hybrid approach works only when it is managed explicitly as a capacity allocation problem, not as a communications tactic.
The critical path: the structural backbone executives cannot wish away
The Critical Path Method identifies the longest sequence of dependent work that determines the minimum duration of a program. In transformation, this critical path is usually dominated by “big rocks”: core technology shifts, foundational data work, identity and access modernization, infrastructure changes, and compliance obligations that must be satisfied before the bank can safely scale new capabilities.
What the critical path optimizes for
- Structural integrity ensuring prerequisite capabilities land in the right order
- Dependency realism making cross-functional coupling explicit across technology, operations, risk, and vendors
- Control and predictability reducing schedule risk by managing the work that moves the end date
Where critical path thinking goes wrong in banks
Critical path rigor can degrade into rigidity when it assumes stable inputs and ignores operational volatility. In banks, resource availability shifts with incidents, regulatory requests, audit findings, vendor delays, and changing risk posture. A static critical path that is not continuously recalculated becomes an optimism artifact: the schedule looks controlled while actual capacity is being reallocated informally.
Another common failure mode is using the critical path as a shield against scrutiny. If critical path language is used to dismiss stakeholder outcomes rather than to explain sequencing, leaders lose sponsorship. The purpose is not to win an argument; it is to protect the minimum viable foundation required to reach the target state safely.
Quick wins: the fuel for momentum, credibility, and learning
Quick wins are high-impact, low-effort interventions that deliver tangible value early. In bank transformations, they often take the form of localized automation, reduction of a recurring pain point, small process redesign, or targeted control instrumentation that reduces friction. Their strategic value is not only immediate benefit, but also proof: proof that the transformation can deliver, proof that teams can change, and proof that governance can operate at speed without compromising control.
What quick wins optimize for
- Credibility visible outcomes that reduce skepticism and strengthen sponsorship
- Culture and adoption early demonstrations that change is practical and worthwhile
- Learning fast feedback on processes, tooling, and operating model assumptions
The quick-win traps that erode transformation outcomes
Quick wins become dangerous when they create shadow portfolios that bypass program governance, consume scarce engineering and change capacity, or introduce localized solutions that increase enterprise complexity. The activity trap is especially common when teams optimize for visible outputs rather than for improvements that move enterprise metrics. A bank can accumulate dozens of quick wins and still fail to shift the underlying cost, risk, and delivery constraints.
Strategic comparison in a capacity-constrained portfolio
- Primary driver critical path prioritizes dependencies and sequencing, quick wins prioritize visibility and buy-in
- Complexity profile critical path work is typically high complexity and cross-functional, quick wins are usually localized and flexible
- Time horizon critical path spans months to years, quick wins span weeks
- Communication logic critical path relies on constraint-based explanation, quick wins rely on value-based evidence
- Worst case a critical path slip moves the end date, quick wins can fragment effort and create non-scalable outcomes
Boards and steering committees should interpret these as different classes of work with different governance needs. The mistake is treating them as interchangeable or allowing one class to starve the other without an explicit, evidence-backed decision.
The winning hybrid approach: dual-track sequencing with hard capacity guardrails
The hybrid approach works when the program treats quick wins as a controlled stream that supports the critical path rather than competes with it. This requires explicit capacity allocation, clear decision rights, and a disciplined definition of what counts as a “quick win” versus what is merely “small.”
1) Sequence first: protect the next dependency that prevents foundation breakage
Leadership teams should identify the next dependency that, if delayed, will create compounding risk later. This is the “must happen next” principle. The critical path is not a list of tasks; it is a set of constraints. If the next constraint is not satisfied, downstream work will either stop or proceed in a way that creates rework and control debt.
2) Run quick wins through pilot lanes with bounded blast radius
Quick wins are most valuable when they operate as pilots that generate evidence without jeopardizing the structural timeline. This means defining pilot teams, limiting cross-system coupling, and requiring that quick wins either (a) improve a measurable enterprise metric or (b) validate a design pattern that will later be scaled through the critical path program.
3) Use real-time adjustment to reflect volatility and capacity shifts
As priorities shift and resources change, the portfolio needs rapid recalculation of what is truly critical. AI-enabled planning tools and modern project practices can help update dependency graphs, highlight schedule risks, and identify where a quick win is consuming a scarce specialist role. The governance goal is not perfect prediction; it is faster recognition of constraint changes and earlier intervention.
4) Convert quick wins into reusable patterns, not local exceptions
The portfolio should treat quick wins as design pattern factories. If a quick win is successful, the program should capture the pattern: architecture choices, control approach, operational process changes, and evidence mechanisms. This makes the quick win additive to the critical path rather than a one-off improvement that cannot scale.
5) Enforce a simple capacity model that makes trade-offs visible
In constrained environments, executives need a shared capacity view that separates (a) mandatory commitments, (b) foundation work on the critical path, and (c) controlled quick-win lanes. A practical guardrail is to cap quick-win capacity and to require that any increase is explicitly funded by a reduction elsewhere, with clear risk acceptance documented.
Governance artifacts executives search for when capacity is the binding constraint
- Critical path dependency map the top sequence of constraints with named owners and escalation triggers
- Capacity allocation view how much delivery and change bandwidth is allocated to foundation, mandatory work, and quick wins
- Quick-win qualification rubric the criteria a proposal must meet to enter the quick-win lane, including measurement, blast radius limits, and pattern capture
- Portfolio risk register where capacity shifts are increasing operational, control, or delivery risk, with decision rights for acceptance
- Evidence dashboard a minimal set of enterprise metrics that show whether momentum is translating into structural outcomes
These artifacts matter because they convert intuitive debate into a governed decision. They also reduce the likelihood of “invisible work” consuming capacity without sponsorship or accountability.
Sequencing confidence for strategy validation and prioritization
Critical path versus quick wins is ultimately a readiness question: what can the bank execute safely, at speed, with evidence, given its current operating model and constraints. When readiness is overestimated, quick wins create fragmentation and critical path work slips. When readiness is underestimated, the bank moves too slowly and loses stakeholder confidence and competitive momentum.
A maturity assessment provides a structured way to test whether the organization can sustain a dual-track portfolio and where capacity constraints will break the model. Used in that context, the DUNNIXER Digital Maturity Assessment can be aligned to the capabilities that determine sequencing success: dependency transparency, delivery discipline, control automation, operational adoption, and governance decision rights. Executives can then place quick wins where they will generate reusable patterns and measurable outcomes, while protecting the critical path foundations that determine whether the transformation can reach a stable, scalable target state.
Reviewed by

The Founder & CEO of DUNNIXER and a former IBM Executive Architect with 26+ years in IT strategy and solution architecture. He has led architecture teams across the Middle East & Africa and globally, and also served as a Strategy Director (contract) at EY-Parthenon. Ahmed is an inventor with multiple US patents and an IBM-published author, and he works with CIOs, CDOs, CTOs, and Heads of Digital to replace conflicting transformation narratives with an evidence-based digital maturity baseline, peer benchmark, and prioritized 12–18 month roadmap—delivered consulting-led and platform-powered for repeatability and speed to decision, including an executive/board-ready readout. He writes about digital maturity, benchmarking, application portfolio rationalization, and how leaders prioritize digital and AI investments.
References
- https://www.projectmanager.com/guides/critical-path-method
- https://www.linkedin.com/pulse/driving-quick-wins-your-pmo-epma
- https://monday.com/blog/project-management/project-management-best-practices/
- https://medium.com/@stepan_plotytsia/ai-and-the-critical-path-method-in-modern-project-management-a884ed13a65a
- https://www.linkedin.com/pulse/transformation-step-2-planning-prioritization-cory-tiede-mba-vbo3e
- https://www.logicalsysinc.com/digital-transformation/building-a-digital-transformation-roadmap/
- https://blog.epmainc.com/driving-quick-wins-for-your-pmo/#:~:text=A%20simplistic%20approach%20that%20includes,centralized%20with%20the%20program%20manager
- https://www.projectmanager.com/guides/critical-path-method#:~:text=In%20most%20projects%2C%20there%20are,affecting%20the%20overall%20project%20timeline.
- https://uplandsoftware.com/psa/resources/blog/deliver-every-project-on-time-with-critical-path-project-management/#:~:text=What%20Is%20Critical%20Path%20Project,want%20to%20finish%20on%20time.
- https://www.goskills.com/Project-Management/Resources/Critical-path-method-project-management#:~:text=What%20is%20the%20critical%20path,resources%20efficiently%20and%20avoid%20bottlenecks.
- https://www.linkedin.com/posts/rwsayrejr_turnaround-valuecreation-privateequity-activity-7394059347267518464-Nm6p#:~:text=Really%20well%20said.,do%20this%20at%201888%20Mills?&text=Effective%20execution%20is%20the%20foundation%20of%20every%20successful%20turnaround%20strategy.&text=Exactly.,Execution%20begins%20where%20slogans%20end.&text=%22Turnarounds%20are%20sequencing%2C%20not%20strategy,Sequence%20%3E%20Strategy%20every%20time.&text=%E2%80%9CToo%20many%20slogans%2C%20too%20little,early%20momentum%20in%20most%20turnarounds.&text=Rob%20Sayre%20Spot%20on.,but%20it's%20what%20saves%20companies
- https://medium.com/@stepan_plotytsia/ai-and-the-critical-path-method-in-modern-project-management-a884ed13a65a#:~:text=Unlike%20traditional%20CPM%2C%20which%20calculates,completions%2C%20or%20changes%20in%20priorities.
- https://www.salesforce.com/blog/steps-digital-transformation-blog/
- https://monday.com/blog/project-management/process-flow/#:~:text=Department%2Dlevel%20flows%20are%20an,from%20product%20design%20to%20engineering.
- https://projectone.com/insights/transforming-change-capability-where-to-start/#:~:text=Quick%20wins%20%E2%80%93%20immediate%20actions%20and,have%20to%20be%20set%20accordingly!
- https://www.pmi.org/learning/library/critical-path-method-calculations-scheduling-8040#:~:text=Critical%20Path:%20The%20continuous%20string,to%20the%20Project%20Completion%20Date.
- https://chartwellagency.com/project-management-strategies-for-staying-on-track/#:~:text=When%20timelines%20tighten%2C%20not%20every,can%20make%20or%20break%20momentum.
- https://www.smartsheet.com/content/critical-path-advantages-disavantages#:~:text=Table_title:%20Disadvantages%20of%20Critical%20Path%20Method%20Table_content:,%7C%20Disadvantages:%20Disadvantages%20Steep%20learning%20curve%20%7C
- https://www.smartsheet.com/construction-critical-path#:~:text=The%20critical%20path%20method%20cuts,the%20critical%20path%20method%20provides.
- https://www.buildingradar.com/construction-blog/understanding-the-critical-path-method-cpm-a-comprehensive-guide#:~:text=The%20Purpose%20and%20Benefits%20of,and%20make%20adjustments%20as%20needed.
- https://www.linkedin.com/pulse/critical-importance-completing-skeleton-works-within-mohamed-0bmff#:~:text=Among%20the%20critical%20phases%20of%20a%20project%2C,early%20structural%20completion%20to%20avoid%20downstream%20disruptions.
- https://www.intrafocus.academy/the-importance-of-quick-wins/#:~:text=Quick%20wins%20boost%20morale%20and%20momentum%0A%0AWith%20a,all%2C%20three%2C%20five%2C%20ten%2Dyear%20goals%20all%20feel%E2%80%A6
- https://www.linkedin.com/pulse/quick-wins-double-edged-sword-organizational-strategy-alsufiany-et7cf#:~:text=Growth%20&%20Efficiency%20Partner%20%7C%20SLS%20Member,tangible%20results%20with%20minimal%20effort%20and%20resources.
- https://www.linkedin.com/top-content/project-management/prioritizing-project-tasks/quick-wins-for-prioritizing-project-tasks/#:~:text=Summary.%20Quick%20wins%20for%20prioritizing%20project%20tasks,worth%20tackling%20first%20for%20the%20biggest%20impact.
- https://www.productlift.dev/blog/product-prioritization-framework#:~:text=impact%2Deffort%2Dnng%20Quick%20Wins%20(High%20Impact%2C%20Low%20Effort):,prioritize%20them%20carefully%20based%20on%20strategic%20importance.
- https://www.linkedin.com/pulse/no-bs-guide-developing-analytics-road-map-ian-howard-auvpf#:~:text=Identify%20Quick%20Wins%20Quick%20wins%20are%20small%2C,secure%20buy%2Din%20for%20the%20broader%20road%20map.
- https://www.meegle.com/en_us/topics/critical-path-method/critical-path-method-for-team-leaders#:~:text=By%20identifying%20the%20critical%20path%2C%20team%20leaders,activities%20that%20directly%20impact%20the%20project%20timeline.